(Week 03/14 – 03/18)
(Week 03/14 – 03/18)
Line 1: Line 1:
  
 
[[Weekly Updates]]
 
[[Weekly Updates]]
 
== Week 03/14 – 03/18 ==
 
 
 
=== This Week ===
 
 
- Defined a modified equipment list with the help of Uli and Jeff at the Danuser lab (simplified design without TIRF and a single laser)
 
 
- Research was made on the best choices for lasers, cameras and objectives
 
 
- The microscope at station 3 was approved for use with the e-STORM project, with minor modifications depending on the specific parts acquired
 
 
=== Next Week ===
 
 
- A final equipment list will be compiled and quotes will be obtained
 
 
- Ideally, the equipment will be ordered
 
 
- Work will start with the image analysis programming, including the analysis of code obtained from the Danuser lab plus literature reading
 
 
=== Risks and Issues ===
 
 
- The adoption of the microscope frame at station 3 might be premature depending on the final parts and design we acquire
 
 
- There might be a fair amount of experimentation with the setup since we are using the most minimalist approach possible
 
 
- There is a delay on the planned time for part ordering, which has to be addressed next week or shipping and processing time might interfere with the project execution
 